Contract TAY 27/2011 – Containerized water treatment plants

Project Description

Design, supply and installation of five (5) containerized mobile water treatment plants at Klirou-Akaki-Malounta and Tamasos dams, total capacity 2500 m3/day.  The treatment method includes multilayer sand and activated carbon filtration with automatic chemical dosing systems.  The system is characterized by its capability to remove inorganic and organic solids in order to achieve colourless/odourless potable water.  The treated water also undergoes disinfection in order to meet potable standards.  The plant is containerized which allows for easy transferability.

Completed

2013

Client

Water Development Department

Location

Tamasos, Klirou

Value / Capacity

€ 524,415